Construction Schedule

The contractor has submitted the following schedule for work.  This schedule may be adjusted based on availability of additional crews.  It may also be adjusted based on weather.

 Street  Concrete Work  Road Work
Clinton Ave  6/13 - 7/15  7/25 - 8/3
Farwood Circle   7/18 - 7/22  8/4 - 8/9
Redwood Ave  7/18 - 7/22  8/4 - 8/9 
Narberth Ave   7/20 - 8/9 8/10 - 8/16 
Beechwood Ave   7/25 - 8/12 8/17 - 8/31 
Bryn Mawr Ave  7/25 - 8/12  8/17 - 8/31 
Friends Ave  8/15 - 9/2  8/29 - 9/9 
Lake St  8/15 - 9/2  8/29 - 9/9